Burns Bay Road Upgrade

Published on 29 August 2024

Burns Bay Road Paving.PNG

Update 3 October - Staging plan update

Council has received feedback from some businesses regarding the timing of the project and to alleviate their concerns the staging of the project has been reversed from what was initially proposed.

Council’s paving contractor will now commence the works in front of Len Wallis Audio and work their way up to the Plaza before crossing road to the Post Office and working their way down toward Tambourine Bay Road. This will mean that the works from Len Wallis Audio to the Plaza should be completed prior to the end of November.

The timing of the tree work at the pedestrian crossing will remain unchanged however, the removal and assessment of Trees 3 to 5 will be brought forward to the week of 14 October.

Council is in the process of providing an updated notification to surrounding residents and businesses.

Update 25 September - Project Commencement Timeframe

Council’s paving contractor will be commencing the Burns Bay Road paving works on Tuesday 8 October (after the October long weekend). The project is  due for completion in December 2024, weather permitting.

The paving portion of the project has been divided into eight stages, commencing on the northern side. To minimise inconvenience and try to maintain as much access as possible to properties and businesses, where possible one stage of paving will be completed before the next one commences. Landscaping works will follow the completion of each stage of the paving works.

A Staging Plan showing the stages of the project is available to view online (please see revised staging plan). This plan is subject to change however is included to demonstrate the various paving stages of the works currently scheduled.

Works will commence with Stage 1 and then continue to move east along the northern side of the Burns Bay Road towards the Post Office before crossing to the southern side of Burns Bay Road to continue west.

The works will be undertaken during the daytime wherever possible; however, to accommodate access to businesses, some works will be required to be undertaken during the night. Hours of works will be between 7:00am and 5:00pm for day works and between 7:00pm and 5:00am for night works. Due to RMS requirements, there may be some movement of heavy machinery outside these hours.

The work will be noisy; however, every effort will be made to minimise the impact of noise on residents and businesses. Where works take place at night, Council’s contractor will endeavour to complete the noisier tasks by midnight.

Access to properties and businesses will remain available for the majority of the project. Access to some properties will be interrupted during the driveway upgrade work and access will likely be unavailable for 24-48 hours. Council’s contractor will provide an advanced notice to those affected residents/business closer to the date of these works.

Most public parking will remain available during the construction however approximately six or seven spaces will be unavailable for the duration of the construction period.

Tree 2 is scheduled to be removed in the week of 14 October and the pavers around Tree 1 will be removed to allow Council's Arborist to assess the extent of the root system and determine whether it can be retained. If it will be required to be removed it will be removed at the same time as Tree 2.

29 August - Burns Bay Road Paving Upgrade

As part of our ongoing streetscape improvements in Lane Cove village, Council will be upgrading the existing brick paved footpath in Burns Bay Road with new granite pavers on both sides of the road, between Rosenthal Avenue and Tambourine Bay Road.

The upgrade aims to remove pedestrian trip hazards while also improving the overall streetscape of the area, including installing paving to match the Plaza and recently completed Longueville Road footpath and dining areas.

Key features of the upcoming works include:

  • Removal of the existing brick pavers on both sides of Burns Bay Road footpath and replacing them with the same granite pavers that have recently been laid in Longueville Road
  • Replacement of all existing concrete driveways within the paved area with granite set pavers
  • New kerb and gutter to address minor flooding issues
  • Installation of pram ramps and leveling of footpath to comply with Disability Discrimination Act requirements
  • Reconstruction of the raised pedestrian crossing and its associated line marking
  • Installation of new garden beds
  • Planting of new native street trees
  • Increasing the size of tree pits around existing and proposed trees
  • Additional seating

In preparation for these works Council's Arborist has assessed all 15 street trees located along this section of Burns Bay Road and determined that 3 will need to be removed and an additional 2 will need to be assessed once works have commenced. 10 new trees will be planted as part of the works, increasing the total number of trees from 15 to 20. Notification signs have been placed on all 5 trees in the event that following excavation the assessment of the two trees requires one or both to be removed.

Council's Arboricultural report is provided in the table below:

Tree Number

Tree Species

Tree Status

Description

1

Sydney Red Gum

(adjacent to crossing)

Retain and investigate

Due to the presence of surface roots, following the excavation process, a below ground investigation will be required to assess the extent of impact on the root system. The results of the assessment may or may not require the tree to be removed.

2

Grey Gum

(adjacent to crossing)

Remove and replace

Poorly formed specimen with an unbalanced canopy distribution and fungal pathogen compromising lower branch attachment.

3

White Gum

(outside Harris Farm)

Remove and replace

The recent upgrade to the local shops has resulted in basal decay, mechanical wounding and close proximity to infrastructure. This tree will not tolerate the pruning required for building clearance or remain viable following the impact of excavation works within the Structural Root Zone and the removal of feeder roots below the existing pavers.

4

White Gum

(outside Pet O)

Remove and replace

The root system of this tree has encroached the middle subsurface layer between pavers and the concrete slab. To successfully remove the trip hazards, this tree will not tolerate or remain viable following the impact of excavation works within the Structural Root Zone and the removal of feeder roots below the existing pavers.

5

Sydney Red Gum

(outside Chemist)

Retain and investigate

The subject tree has a girdled root system that leads to a stunted and suppressed specimen. Due to the presence of further surface roots, following the excavation process, a below ground investigation will be required to assess the extent of impact on the root system. The results of the assessment may or may not require the tree to be removed.

A summary plan showing the extent of the works and location of new tree planting, trees to be further assessed and trees to be removed is available to view online.

Council has engaged a contractor to undertake these works and we are expecting them to commence in October 2024. Once the start date is confirmed it will be posted on this webpage.

To minimise inconvenience to residents and shop keepers, construction will be staged into manageable sections with one section of paving being completed prior to the next section commencing. The tree planting and landscape works will occur after the paving works have been completed.

Tagged as: